Proposed Timeline

for development of

Nationwide Process Service

Web Enabled

Office Automation System

13 June 2005

Overview


Phase 0 - Agreement of Terms and Timeline - $2000

Both Nationwide and the Development Team agree to:

Phase 1 - Internal Office Automation Package

Phase 1, Stage 0, Nationwide: Order Hardware

Hardware to be provided by Nationwide, meeting specifications set be the development team.

Phase 1, Stage 1, Development Team: Data Conversion Programs - $1000

Phase 1, Stage 1 Approval: Approve Data Conversion routines

Phase 1, Stage 2, Development Team: Initial Hardware Installation and Configuration - $2500

The Development Team will perform the initial installation and configuration off site. Upon completion of initial installation and configuration, the hardware will be installed in it's destination sites.

Phase 1, Stage 2 Approval: Initial Hardware Installation and Configuration

Phase 1, Stage 3, Development team: Primary Internal User Interface - $1000

Phase 1, Stage 3 Approval: Internal User Interface

Phase 1, Stage 4, Development team: Statements and Receivables - $1000


Phase 2 - External Client Web Access


Phase 3 - Future Development NOT Covered by this Contract


Modules: